EXPERIENCE |
|
|
|
Mosler
Safe-Hamilton, OH |
|
Clean Ohio
Revitalization Fund - Complete asbestos abatement and removal of 15,000 Lf of
thermal system insulation; 50,000 LF of transite board; 25,000
LF of acoustical plaster as well as recovery and recycling of
fluorescent bulbs and ballasts. |
|
|
|
Kettering School district - Kettering, OH |
|
Various Projects - Complete abatement and removal of 15,000
LF of asbestos containing ceiling tiles, 7,500 LF of floor tile
and mastic. Removal and recovery of fluorescent bulbs and PCB ballasts. |
|
|
|
|
|
|
|
|
|
Terminal
Management - Cincinnati, OH |
|
Removal and disposal of 20,000 LF of asbestos containing
thermal systems insulation and 3,000 SF acoustical plaster.
Demolition and removal of all heating units and associated
piping. |
|
|
|
University
Hospital - Cincinnati, OH
|
|
Various Projects - Complete removal and disposal of 2,500 LF
of asbestos containing thermal system insulation: 6,000 SF of
floor tile and mastic; and 2,500 SF of acoustical plaster. |
|
|
|
West Clermont Local School District – Cincinnati, OH |
|
Perform operations and maintenance of facilities district-wide. |
|
|
|
|
|
|
|
|
|
Wright Patterson Air Force Base – Dayton, OH (Area B) |
|
Removal of asbestos containing pipe insulation, floor tile mastic and acoustical
ceilings. |
|
|
|
Colliers International |
|
Remove asbestos contaminated materials to allow demolition phase to
maintain proposed schedule. |
|
|
|
|
|
|
|
|
|
University of Dayton – Marycrest Hall, Phase I |
|
Removal and disposal of asbestos pipe insulation, floor tile and
mastic. Demolition of the core washroom facilities on all seven
floors. Mechanical demolition in lower service areas. Work
performed and completed in the specified timeframe. |
|
|
|
Brighton Center – Messer Construction, Butler, KY |
|
Remove asbestos containing materials throughout the structure and
boiler facilities. Completely gut the facility to allow
state-of-the-art renovation process. Completely remove the front
façade of the structure. Work performed in a timely fashion while
encountering winter weather. |
|
|
|
|
|
|
|
|
Schumacher Dugan Construction – Cincinnati, OH
Operators Union Local 18 Main Offices |
|
Remove asbestos floor tile and mastic in multiple phases to allow
normal operations to continue. Work was performed ahead of schedule
in all phases. |
|
|
|
Cincinnati Bulk Terminal – Cincinnati, OH |
|
Remove all exterior transite panels while using lifts and heavy
equipment. Procedures were followed to prevent accidents including
working 30 feet over the Ohio River while the client’s daily
operations remained intact. |
|
|
|
|
|
|
|
|
|
Walgreens Corporation – Cincinnati, OH |
|
Full negative pressure containment for removal and disposal of
mold contaminated drywall board and framing, carpet, ceiling
tiles and vinyl flooring. After removal, the entire area was HEPA vacuumed, cleaned and encapsulated with an anti-microbial
agent. |
|
|
|
CVS Drugstore - Columbus, OH |
|
Full negative pressure containment for removal and disposal of
mold contaminated drywall board, fiberglass insulation and
framing, carpet, ceiling tiles, cabinetry and vinyl flooring.
After removal, the entire area was HEPA vacuumed, cleaned and
encapsulated with an anti-microbial agent. |
|
|
|
Gambro Health Care - Cincinnati, OH |
|
Removal and disposal of mold contaminated dry wall board and
frame, ceiling tile and grid system, vinyl flooring. All exposed
surface were wiped down, HEPA vacuumed, cleaned and encapsulated
with an anti-microbial agent. All work was performed under full
negative pressure containment preventing cross
contamination. |
|
|
|
Kinder Care Knowledge Learning Center |
|
Removal and disposal of mold contaminated dry wall board and
frame, ceiling tile and grid system, vinyl flooring. All exposed
surface were wiped down, HEPA vacuumed, cleaned and encapsulated
with an anti-microbial agent. All work was performed under full
negative pressure containment preventing cross
contamination. |
|
|
|
Clear Channel, Inc - Dayton, OH |
|
|
|
Corporex, Inc. - Florence, KY |
|
Remove mold-impacted drywall in renovated areas. Treat remaining
surfaces to prevent future growth. |
|
|
|
Chuck E. Cheese Corporation – Southern OH, Kentucky, Tennessee |
|
Provide assistance during renovation process in the event
mold-impacted materials are discovered. Disinfect and sanitize
areas upon completion. |
|
|
|
Walgreen’s Corporation – Cincinnati, OH and Hartwell, OH |
|
Remove impacted materials from lower levels of facilities.
Disinfect and treat areas for a clean final product. |
|
|
|
|
|
|
|
|
|
Stephen Bell
Elementary – Kettering, OH |
|
Compete interior demolition of dry wall partitions and framing,
plaster ceilings, concrete slabs. Load bearing CMU walls and all
flooring. |
|
|
|
Madeira High School – Madeira, OH |
|
Compete interior demolition of dry wall partitions and framing,
plaster ceilings, concrete slabs. Load bearing CMU walls and all
flooring. Cutting of metal roof deck penetrations for the
addition of new mechanical. Site work demolition included
removal of sidewalks and parking lot while providing clean fill
and final grade. |
|
|
|
Biggs Supermarket – Delhi Location, Cincinnati, OH |
|
Full interior gut out of Kmart store for the future Biggs
retail/grocery store. Demolition included removal of all dry
wall partitions, ceilings, restrooms, concrete slabs, flooring
and mechanical equipment. |
|
|
|
580 Building - Cincinnati, OH |
|
Multi-level downtown Cincinnati office building. Demolition and
removal of drywall partitions and framing, flooring, ceilings,
plumbing fixtures and pipes, mechanical equipment and duct work.
Dismantling and removal of two storey vault, escalators, and
elevators. Also demolished and removed were concrete slabs,
roofing, brick and CMU block facades well as some miscellaneous
site work. |
|
|
|
|